New service · Step-by-step guide
How to get electric service to a new home
Getting power to a new home, barn or shop takes seven steps: apply with your electric utility, get the utility's site visit and service point, hire an electrician and pull permits, install the mast or trench, meter base, disconnect and grounding, pass inspection so the release goes to the utility, have the utility connect and set the meter, then energize and test. Apply with the utility first, before you break ground.
Where does the utility's job end and yours begin?
Most disputes with a power company come down to one boundary: the service point. The utility sets it during its site visit. Everything on its side (primary line, pole or pad-mount transformer, service drop or lateral, and the meter) is the utility's equipment and cost. Everything on your side (mast or conduit, meter base, disconnect, panel and grounding) is yours to buy, install through a licensed electrician, get inspected and maintain. See who owns the service line for details.
Requirements vary by utility. Trench depth, meter height, conduit schedule and who supplies the conductors are set by your power company and your local inspector. Use this guide to understand the order, then confirm every dimension in your utility's service manual.
The 7-step process
Apply for service with your electric utility
Everything starts with the power company, not the electrician. File a new-service or line-extension application as soon as you have a site plan. Engineering queues, easements and transformer lead times are often the longest items on the whole build.
- Have the address or parcel number and a site plan showing the building, driveway and property lines.
- Say what service size you want (200 A or 400 A class) and whether you want overhead or underground.
- Ask for the utility's residential service requirements manual. Every dimension you will be held to is in it.
Utility site visit, service point and cost estimate
A utility planner walks the property and sets the service point: the pole for an overhead drop, or the pad-mount transformer location for an underground run. You get a design, conduit and trench specs, an approved meter location and a written estimate for any line-extension charges.
- Get the service point, meter height and conduit size in writing before you dig or buy material.
- Clear and stake the route. Utilities won't set a transformer or pull cable through an obstructed path.
- Confirm who supplies the conduit and the service conductors.
- Pay construction charges promptly. Most utilities won't schedule work until the invoice clears.
Hire a licensed electrician and pull permits
Your electrician pulls the electrical permit and is responsible for everything on your side of the meter. Size the service with a real load calculation now. Undersizing means paying for an upgrade later; oversizing means paying for capacity you never use.
- Check license, bond and insurance, and make sure the permit is in the contractor's name.
- Run a load calculation for square footage, HVAC, range, dryer, water heater, EV charger, hot tub and shop loads.
- Make sure the permit and the utility design agree on meter location and service size.
Install the mast or trench, meter base, disconnect and grounding
This is the physical build, and it is where overhead and underground services differ. Build to the utility's specs, not to what worked on the last job. These details are exactly what the inspector checks.
- Overhead: mast and weatherhead at the required height, strapped riser, drip loops and drop clearances.
- Underground: trench to the required depth, PVC conduit of the required schedule, long-radius sweeps, expansion fitting, pull string and warning tape.
- Both: a utility-approved meter base set plumb at the approved height, with an outdoor service disconnect under the 2026 NEC.
- Grounding: usually two 8 ft ground rods at least 6 ft apart, plus the footing electrode and water pipe bond where present.
- Leave the service conductors long so the utility can terminate them cleanly.
Pass inspection and get the release (green tag)
The inspector checks the service equipment, grounding, bonding and conductors, and on underground jobs the open trench before backfill. When it passes, the inspector sends an electrical release to the utility. Without that release, no utility will connect.
- Schedule the trench inspection before backfilling. Reopening a covered trench is the most expensive rework on an underground service.
- Common failures: loose or missing ground clamps, wrong conduit schedule, meter outside the height range, unsupported riser, missing bonding jumper.
- Call the utility to confirm the release arrived. Don't assume it was sent.
Utility connects the service and sets the meter
An overhead crew runs the service drop from the pole to your weatherhead. An underground crew pulls the lateral from the transformer through your conduit and lands it in the meter base. Then the meter goes in and the service is live.
- Never break a meter seal or set your own meter. The meter belongs to the utility.
- Make the site accessible on the scheduled day: gates unlocked, dogs contained, route clear.
- Open the billing account in the right name. A missing account is a common reason a crew never shows up.
Energize, test and document
With the meter set, the electrician turns on the main and commissions the system. This is the difference between a service that is merely live and one that is finished and documented.
- Verify about 240 V between the two hot legs and 120 V from each leg to neutral.
- Torque every lug to the manufacturer's value. Loose lugs are a leading cause of meter base and panel failures.
- Test GFCI and AFCI devices, and confirm neutral and ground are bonded only at the service disconnect.
- Label the panel directory and file the permit, inspection card and utility work order together.
What size service should you ask for?
Most new homes get 200 amps. All-electric homes with heat pumps, EV chargers and large shops often need a 400-amp (Class 320) service. Get a rough number with our service size calculator before step 1, and read 200 amp vs. 400 amp service.
Next: the underground service guide, the overhead service guide and the full parts list.
Frequently asked questions
How long does it take to get electric service to a new house?
Plan on several weeks to several months. The physical work takes only a few days, but utility engineering, easements, construction charges and transformer lead times often take the longest. Applying with the utility before you break ground is the single biggest way to shorten the schedule.
Who do I call first to get power to a new build?
Call the electric utility that serves the parcel first, then your electrician. The utility sets the service point, meter location, conduit size and trench depth, and your electrician needs those details before ordering material or pulling the permit.
What is a green tag or electrical release?
It is the inspector's approval of your new service, sent to the utility. Without it, the utility will not connect power or set the meter, no matter how finished the building is. After you pass inspection, call the utility to confirm they received it.
How much does it cost to run electric service to a new house?
It varies widely. Short overhead services may cost a few thousand dollars, while long underground runs with a new transformer and line extension can cost tens of thousands. The utility's written estimate in step 2 and your electrician's bid in step 3 are the real numbers.
Sources: AEP, Guide for Electric Service and Meter Installations (2026); NFPA 70 (NEC) 2026, Articles 120, 230 and 250.